BMS Building Project Blog: Week of July 21, 2019

Week of July 21, 2019: 

Week 75 - 

As we enter into the 75th week of construction, we can look forward to the following:

  • Phase 1

  • Continue to maintain sediment erosion control around the perimeter of the construction site.

  • A/E Punch List; Section C & D

  • Install Stage Flooring in Auditorium

  • Install Auditorium Equipment

  • Install Auditorium Lighting

  • Paint: Section A & B & C & D

  • Test Fire Alarm Devices

  • Install Exterior Light Fixtures

  • Install Access Control

  • Maintain Landscaping

  • Rooftop Unit Commissioning

  • Furniture Deliveries

  • Equipment Deliveries

  • Install Telephones

  • Install Classroom A/V

  • Noise level: Landscaping and Heavy Equipment Operators

  • Phase 2 Began June 24, 2019

  • Continue to maintain sediment erosion control around the perimeter of the construction site.

  • Remove Bituminous Roads

  • Demolition Process in Zone 1

  • Demolition Process in Zone 2

  • Demolition Process in Zone 3

  • Install Light Pole Bases

  • Temporary Construction Fence Installation

  • Tree Protection

  • Tree/Brush Removal

  • Noise level: Heavy Equipment Operators

Student Union with tables!

Kitchen looking great with equipment! 

Art room with supplies that were delivered from our old school! 

Presentation room! 

Math classrooms configured with flexible furniture. 

ELA Classroom looking great! 

Achievement! 

Science classroom with lab tables. 

Flexible furniture in our business lab! 

Lights being installed in our auditorium! 

Flexible furniture in our larger breakout spaces!

Teacher materials have arrived! 

Bookshelves installed and boxes ready to be unpacked! 


Dr. Anderson with the double thumbs up!