Week of July 21, 2019:
Week 75 -
As we enter into the 75th week of construction, we can look forward to the following:
Phase 1
Continue to maintain sediment erosion control around the perimeter of the construction site.
A/E Punch List; Section C & D
Install Stage Flooring in Auditorium
Install Auditorium Equipment
Install Auditorium Lighting
Paint: Section A & B & C & D
Test Fire Alarm Devices
Install Exterior Light Fixtures
Install Access Control
Maintain Landscaping
Rooftop Unit Commissioning
Furniture Deliveries
Equipment Deliveries
Install Telephones
Install Classroom A/V
Noise level: Landscaping and Heavy Equipment Operators
Phase 2 Began June 24, 2019
Continue to maintain sediment erosion control around the perimeter of the construction site.
Remove Bituminous Roads
Demolition Process in Zone 1
Demolition Process in Zone 2
Demolition Process in Zone 3
Install Light Pole Bases
Temporary Construction Fence Installation
Tree Protection
Tree/Brush Removal
Noise level: Heavy Equipment Operators
Student Union with tables!
Kitchen looking great with equipment!
Art room with supplies that were delivered from our old school!
Presentation room!
Math classrooms configured with flexible furniture.
ELA Classroom looking great!
Achievement!
Science classroom with lab tables.
Flexible furniture in our business lab!
Lights being installed in our auditorium!
Flexible furniture in our larger breakout spaces!
Teacher materials have arrived!
Bookshelves installed and boxes ready to be unpacked!
Dr. Anderson with the double thumbs up!